Condition of the building before construction started.
Construction Starts
This point has taken forever to get to.
It was a very long and bumpy road, but we are where we want to be .
We removed the stairs and the load bearing wall was extended out.
Stainless Steel shelving will hang on the 2 x 8 in the walls, just above the stainless tables.
$7,000.00 in metal doors
Hand sinks support in the walls.
Plumbing… with floor drains added…
Electrical and structure will be finished by the end of this week. We need to frame out my office and the break room, both are upstairs.
ETA is October the 1st, we shall see about that.
35 Likes
I see progress. Good to see you back
7 Likes
I hope you keep my graffiti
13 Likes
How’s your engineer treating you?
5 Likes
Putting in some work. looking great.
2 Likes
Nice work.
I kinda dig the previous look, though.
Except for the wiring.
11 Likes
Jc1944
August 31, 2021, 2:48am
7
Congrats and keep killing it solid work. This is for analysis right? Anyway keep up the good work!
1 Like
That depends on how quickly we get your non detect D8 Distillate.
2 Likes
The crazy thing is… the previous tenants, were auto painters… that big room in the very first pic was their paint booth.
Everyday, I listen to my carpenter bitch about kilz paint and how he cant wait to use it…lol
5 Likes
MY OFFICE
STORAGE SPACE
BREAK ROOM
The AC units have been delivered. Going to be fun installing them over the next few days.
Had a COVID set back, I had to keep the daughter home for ten days because of an outbreak at her school. Turns out my electrician had COVID on my job site (the last day we worked together) and passed away a few days ago.
22 Likes
God damn you’re moving fast
I just got the heads up no school on the 20th randomly
Love seeing the growth brother. Miss Texas and my favorite travel stop.
4 Likes
We are at 70 pounds of screws at this point. LOL
Edit…100 pounds of screwed now.
7 Likes
Hope to see it when I come in for the Texas Hemp Convention.
4 Likes
If its not done by then, I’m jumping of a bridge. I can’t wait to show you around. Note to self, extra TALL scrubs needed on stand-by.
The Daughter and I had a blast during the week long Daddy Daycare episode.
Here is a snip-it of the week.
We had a big photo shoot that week
15 Likes
I’m hoping to maybe swing by to pick up my date from the airport for a wedding in Texas during the middle of October. You’ll appreciate meeting
1 Like
Congrats on the build, sorry to hear about the electrician
8 Likes
I missed that part… that is horrible.
@MillerliteRN Looks like plenty of work to do after the building is done.
Maybe I can lend a hand in my extra tall scrubs haha
2 Likes
Yeah, it’s a shame. The guy literally left his equipment at the jobsite as he went home not feeling well. Turns out the apprentice thought he had allergies for a few days prior.
Thank God for all the big fans, moving shit tones of air around. Cause we definitely had a few regular type close conversations around the jobsite for two days.
9 Likes
Wow I missed that last bit. Rest in Peace.
1 Like