Oklahoma LP Gas Board

Hello what’s up everyone. So as everyone knows in order to be able to keep running your lab you need to get signed off by the LP Gas Board. We have our c1d1 booth but don’t have a asme system, Ive heard from a few different people that a peer review will do, but have had a few others say that an ASME system is required to get signed off. Does anyone have any solid info?

Ask the AHJ

This is an email I got from the oklahoma gas administration asking for the requirements to obtain a class 6 permit. Peer review should be fine as that’s what they say they require.

5 Likes

Thanks man appreciate it

1 Like